Contact

Stay Connected
  • mail
  • skype
  • msn
  • google
  • facebook
  • twitter
  • in
  • xml
  • p
Mercedes-Benz’s Factory Project Site:Home >Projects

 

 
Cooperation with Beijing Benz Automotive Co., Ltd.
----New achievement in automotive plant air conditioning industry

Project introduction:
HOLTOP cooperated with Beijing Benz Automotive Co., Ltd. by providing more than 90 sets of combined air handling unit with digital automatic control system for the plant expansion and R&D centre project. All of the design, purchasing, manufacturing, assembling and initial commissioning are accomplished within 90 days, our timely delivery, profession and high quality earn recognition and praise of our respected customers at home and abroad, which shows our strength of technology, manufacturing and quality in the filed of heat recovery.
benz-01.jpg


Features of air handling units in this project:
- Constructed by aluminum alloy framework, thermal insulation and double skin panels;
- Cold bridge factorcomplys with EU TB2 standards;
- Air leakage rate less than 1%;
- Double fans application for space saving;
- Silencer equiped before and after fans to reduce noise effectively;
- Double cleaning of air and water for heat recovery wheel, insuring durable high heat recovery efficiency;
- VFD control of supply and exhaust fan to make constant air pressure supply for more energy saving;
- VFD control of heat recovery wheel to prevent ice blockage in winnter;
- The whole unit was controlled by mechatronics digital automatic control technology with higher accuracy and precision.


 

benz-02.jpg

HOLTOP cooperated with Beijing Benz Automotive Co., Ltd

   

benz-03.jpg

80,000 m3/h AHU

 

benz-04.jpg

AHU delivery

   

benz-05.jpg

Site installation

 

benz-06.jpg

Installation finish

   

benz-07.jpg

Site commissioning and hand over